How this page was made. Jordan Hale is the author and is responsible for this page. An AI assistant helped gather public guidance from manufacturers, codes and extension services, and draft the steps. That is assistance, not hands-on experience. The author name is a pen name, and this site does not invent an expert persona or credentials. The illustration at the top is AI-generated and shows the general idea, not exact construction details; the labeled diagrams are drawn for this page.

This is the order of work for a small, ground-level slab such as a patio, walkway or shed pad, poured from bagged mix or a small ready-mix load. It isn’t a guide to footings for an addition or a garage. Those follow your building code and usually need a permit and an inspection.

Before you start. Call 811 a few business days before you dig. Ask your city or county whether the slab needs a permit or must sit a set distance from property lines. Wet concrete is caustic. OSHA warns it can cause serious chemical burns, so wear waterproof gloves, long sleeves and eye protection.

1. Work out how much to buy

Use the concrete calculator. A 10 × 10 ft slab at 3½ in is 29.2 ft³: 49 × 80 lb bags before waste, 52 with 5%. One cubic yard is 45 × 80 lb bags. Around that size, think about a rented mixer or ready-mix.

2. Lay out and check the slope

  1. Mark the outline with stakes and mason’s string. Square the corners with the 3-4-5 method: mark 3 ft along one string and 4 ft along the other; the diagonal between the marks should be exactly 5 ft.
  2. Level the strings with a line level, then lower them on the far side to build in slope. QUIKRETE uses 1/8 in per foot as a standard slope. Next to a house, the IRC requires impervious surfaces within 10 ft of the foundation to slope at least 2% away from the building. That’s about ¼ in per foot, twice QUIKRETE’s figure, so use ¼ in per foot there.

3. Dig and build the base

Cross-section of a small slab: 3½ inches of concrete inside 2×4 forms staked every 3 feet, on 4 inches of compacted gravel over soil, sloping away from the house, with a control joint cut a quarter of the slab depth.
Typical small-slab section based on QUIKRETE’s patio instructions.
  1. Strip sod at least 6 in beyond the strings so the base extends past the slab.
  2. Dig to a consistent depth below the strings. For 2×4 forms, that’s 7½ in: 4 in of base plus 3½ in of concrete.
  3. Spread about 5 in of compactible gravel and tamp it down to 4 in. Soft, sandy or clay soil may need more work. Dig a test hole first. The gravel calculator gives tons for the base.

4. Set the forms

  1. Cut 2×4s so their inside faces match the slab size, with the inside edges directly under the strings.
  2. Drive stakes every 3 ft on the outside and screw through them into the boards. Level across the forms, keeping the slope you set.
  3. Coat the inside faces with release agent or vegetable oil.
  4. Where the slab meets the house, a step or a wall, glue ½ in asphalt-impregnated fiber board to the structure as an isolation joint.
  5. Mark control-joint positions on the outside of the forms (see step 6).

5. Pour, screed and float

  1. Dampen the base without leaving puddles. Mix to the water amount on the bag and fill the forms a section at a time.
  2. Screed: saw a straight 2×4 back and forth across the forms to strike off excess concrete.
  3. Float once the shine of bleed water has gone. Working the surface while water is still on top weakens it.
  4. Run an edger along the forms. For grip, finish with a broom; for a smooth surface, use a steel trowel.

6. Cut control joints

Concrete shrinks and cracks. Control joints make it crack in a straight line where you choose.

7. Cure it

Curing means keeping water in the concrete while it gains strength. Either apply a cure-and-seal product as soon as the surface sheen is gone, or keep the slab continuously damp. NRMCA says curing should continue for at least 3 to 7 days, longer in cool weather. Don’t let it alternate between wet and dry.

Sources

Questions worth answering

How thick should a patio slab be?

QUIKRETE's patio project uses 3½ in of concrete (the height of 2×4 forms) on 4 in of compacted gravel. Driveways, garage floors and slabs under structures are often thicker and may be set by local code or a permit, so check before you pour.

Do I need rebar or wire mesh?

QUIKRETE lists rebar as optional for a patio and says fiber-reinforced crack-resistant mix can replace wire mesh. Reinforcement doesn't stop cracking; control joints decide where cracks go.

How soon can I walk or drive on it?

It depends on the mix and the weather. Sakrete rates its High-Strength mix for foot traffic after 24 hours and vehicles after 72 hours. Keep curing it either way.